Getting started

The editor at a glance
| Area | What you find there |
|---|---|
| Top bar | Back to the Dashboard, diagram name and save status, Undo and Redo, the Select, Connect and Text tools, Templates, dark mode, Help, Share, the active case, the view mode, the balance status, Export and Save. |
| Left panel | Basic shapes, your own images and 290 equipment symbols in three styles. See Symbols and shapes. |
| Canvas | Your diagram. Drag the empty canvas to pan, scroll to zoom. See Canvas, saving and files. |
| Right panel | Properties of what is selected: a node, several nodes (with alignment), or an arrow with its stream data and balance. |
| Floating toolbar | Appears under a selected node: duplicate, bring to front, send to back, rotate by 90° and delete. |
| Bottom bar | Zoom, Fit, grid style, Snap to grid and connection Handles. The minimap sits in the corner. |
Your first diagram in six steps
- Click Templates to start from a ready flowsheet, or start with an empty canvas.
- In the left panel choose a symbol style (3D, 2D or Simplified) and click a symbol, for example Ball Mill. It appears in the middle of the view. Drag it into place.
- Add the other units the same way. Turn on Snap in the bottom bar so they line up on the grid.
- Choose Connect in the top bar, click the first unit and then the second. A stream arrow is drawn between them. Press Escape or choose Select to stop connecting.
- Click a unit or an arrow and adjust it in the right panel: name, colours, size, arrow style and stream data.
- Name the diagram by clicking its title in the top bar, then press Save (Ctrl+S). It is stored in your account and listed in the Dashboard.

Symbols and shapes

Three symbol styles
| Style | Looks like | Good for |
|---|---|---|
| 3D | shaded isometric equipment | presentations, proposals, websites |
| 2D | flat coloured drawings | reports and manuals |
| Simplified | black line drawings in the ISO / PFD style | engineering documents and printing |
You can mix styles in one diagram, but a single style looks more professional. The style you choose is remembered for the next time.
Finding a symbol
| Tool | How it works |
|---|---|
| Search | Type part of the name, for example thick or cyclone. The search covers all 290 symbols in all styles. |
| Areas | General (comminution, classification, separation, storage, transport), Hydromet (leaching, CIL/CIP, SX/IX, precipitation, tanks), Pyromet (roasting, smelting, converting, slag, refining, off-gas, handling) and Recycling (sorting, battery, e-waste, storage). |
| Categories | Narrow an area down, for example Hydromet → Leaching. |
| Favourites ★ | Hover a symbol and click the star. All starred symbols are collected under ★ Favourites, separately for each style. |
Click a symbol to place it in the middle of the current view. Hover it to see its full name.
Basic shapes
| Shape | Typical use |
|---|---|
| Box | a general process step, a unit without a symbol, a legend |
| Device | orange box for equipment or instruments |
| Circle, Ellipse | start and end points, sample points, tanks drawn schematically |
| Diamond | decisions and splits in block diagrams |
| Triangle, Arrow | stockpiles, direction marks |
| Pill | feeds and products, for example “ROM ore” or “Cu concentrate” |
| Text | free text without a frame: titles, notes, area names |
Your own images
Click Image to upload a picture from your computer, for example your company logo, a photo of the plant or a symbol you drew yourself. It is placed in the middle of the view and can be moved, resized, rotated and connected like any other node. Images are saved inside the diagram, so keep them small (a few hundred kB).
Editing equipment and shapes

Select, move, resize, rotate
| Action | How |
|---|---|
| Select | click the node (the Select tool must be active) |
| Move | drag it; with the arrow keys 1 px, with Shift + arrow 10 px |
| Resize | drag the orange handle in the bottom-right corner. The proportions are kept, so symbols never get distorted |
| Rotate freely | drag the round handle above the node |
| Rotate exactly | type the angle in Rotate in the right panel, or click ↻ in the floating toolbar for 90° steps |
| Rename | double-click the node and type |
| Deselect | click the empty canvas or press Escape |
Properties

| Field | Meaning |
|---|---|
| Label | the name shown under (or inside) the node |
| Fill, Border | background and outline colour of shapes |
| Text, Font | colour and size of the label |
| W, H | width and height in pixels |
| Radius | corner rounding of boxes (0 = sharp) |
| Rotate | angle in degrees |
Shapes have fill and border colours; equipment symbols keep their drawing and only the label can be styled.
Floating toolbar and right-click menu

| Command | What it does |
|---|---|
| Rename | edit the label |
| Duplicate (Ctrl+D) | a copy next to the original |
| Bring to front / Send to back | change which node is drawn on top, for example to put a panel behind the equipment |
| Rotate 90° | in the floating toolbar |
| Delete | removes the node together with its arrows |
Equipment tag and process data
Under Process data enter the tag (for example ML-101), the throughput with its unit (t/h, m³/h, kg/h, Mt/a, t/d, m³/d) and the installed power in kW. The tag is shown in orange under the label and the values below it; untick Show to hide them on the drawing. Export → Equipment list writes every unit with its tag, symbol style, throughput and power into Excel, with the total installed power.
ML-101 for mill 1 in area 100. The equipment list and the balance tables are sorted by tag and stream number.Arranging and aligning
Selecting several nodes
| Action | How |
|---|---|
| Add to the selection | Shift + click each node |
| Select everything | Ctrl + A |
| Move together | drag any of the selected nodes, or use the arrow keys |
| Copy and paste | Ctrl + C, Ctrl + V. Arrows between the copied nodes are copied too |
| Duplicate | Ctrl + D |
| Delete | Delete or Backspace |

Align and distribute

| Button | Result |
|---|---|
| ← Left, Right → | left or right edges in line |
| ↔ Center | vertical centre lines in line (one under another) |
| ↑ Top, Bottom ↓ | top or bottom edges in line |
| ↕ Middle | horizontal centre lines in line: the usual choice for a process train |
| Distribute H / V | equal gaps between the nodes, horizontally or vertically. The first and last node stay where they are |


Grid and snapping
Snap in the bottom bar moves nodes on a 20 px grid while you drag them, so rows and columns line up by themselves. Grid switches the background between lines, dots and no grid. The grid is never exported.
Layers
Nodes are drawn in the order they were added. Use Bring to front and Send to back to change it. A typical use is a large light Panel or box sent to the back to frame an area such as “Grinding” or “Flotation”.
Tips for a professional flowsheet
- Flow from left to right (or top to bottom), with feed on the left and products on the right.
- One row per process train: use Middle and Distribute H.
- Recycles below the main line, drawn dashed; water and reagents come from the top, tailings go down.
- Group areas in panels with a short title in capitals.
- Same style, same size: one symbol style and similar sizes for similar equipment.
- Number the streams in the direction of flow (S1, S2 …) and tag the equipment.
Connecting streams
Drawing an arrow
- Choose Connect in the top bar.
- Click the unit the stream leaves. Click near the side you want it to leave from (with Handles on you see the four connection points).
- Click the unit it goes to, again near the side where it should enter.
- Repeat for the next stream. Press Escape or choose Select to finish.
The new arrow takes the style chosen in the arrow style selector. If you click in the middle of a unit, PfdLabs picks the sides facing each other.
Arrow styles
| Style | Use |
|---|---|
| Smooth Angle | the standard for flowsheets: right angles with rounded corners. Used in all templates. |
| Angle | right angles with sharp corners, the classic engineering look |
| Straight | short direct connections |
| Smooth, Curved | block diagrams and sketches |
Ports
Every unit has four ports: North, East, South, West. Select an arrow and set From Port and To Port in the right panel. Changing ports is the main way to route arrows neatly: a recycle from the cyclone underflow back to the mill looks best from South to South, a feed from East to West, a water addition from North (from above).

Look of the arrow
| Field | Options |
|---|---|
| Label | text in the middle of the arrow, for example “overflow”. Double-click an arrow to edit it |
| Color, Width | any colour, line width in px |
| Arrow | none, at the end, at the start or both ends |
| Line | solid, dashed or dotted |
Delete edge removes the arrow; selecting it and pressing Delete works too.
Colour and line conventions
There is no single standard, but these are widely understood:
| Stream | Suggested look |
|---|---|
| Ore and slurry, main process | grey or dark blue, solid |
| Recycle (circulating load, cleaner tails) | orange or red, dashed |
| Water | blue, solid |
| Solutions (PLS, raffinate, electrolyte) | cyan |
| Organic | yellow |
| Reagents | green, thin |
| Air, gas, off-gas | light grey, dotted |
| Signals, control lines | dotted, thin |
Stream data
Each arrow also carries stream data: stream number, flow with its unit and % solids, shown as a label on the drawing (untick Show to hide it). On Yearly and Lifetime plans the same arrow holds the balance inputs. See Mass balance basics.
Canvas, saving and files
Navigating the canvas
| Action | How |
|---|---|
| Pan | drag the empty canvas |
| Zoom | mouse wheel (zooms around the cursor) or + and − in the bottom bar |
| Fit | Fit in the bottom bar shows the whole diagram |
| Minimap | the small overview in the corner; the orange frame is your view. Click it to fit |
| Dark mode | the Dark button in the top bar. Exports always have a white background |

Saving
- Save (Ctrl+S) stores the diagram in your account. The status next to the name shows Saved or Unsaved changes.
- Autosave runs every 30 seconds for Pro users, and for Free users once a diagram has been saved the first time.
- Undo and Redo (Ctrl+Z, Ctrl+Y) keep the last 50 steps.
Dashboard
The Dashboard lists your diagrams. Open, rename, duplicate or delete them there. The Free plan keeps 5 diagrams in the cloud, Pro plans are unlimited.
Files
| Command | What it does |
|---|---|
| Export → Download as file (.json) | saves the complete diagram, including stream data, balance settings and cases, as a file on your computer. Unlimited on every plan |
| Export → Open file… | opens such a .json file again |
| New diagram | clears the canvas after asking |
| Templates | opens a ready flowsheet |
Phones and tablets
The editor is made for a computer with a mouse. On a phone you can open it, but a note recommends a larger screen. Shared links (Share) work well on phones.
Keyboard shortcuts
| Keys | Action |
|---|---|
| Ctrl + Z / Ctrl + Y | Undo / redo |
| Ctrl + S | Save |
| Ctrl + C / Ctrl + V | Copy and paste the selection with its arrows |
| Ctrl + D | Duplicate |
| Ctrl + A | Select all |
| Delete / Backspace | Delete the selection |
| Arrow keys | Move 1 px (with Shift 10 px) |
| Escape | Deselect or stop connecting |
| Shift + click | Add to the selection |
| Double-click | Rename a node or edit an arrow label |
| Right-click a node | Context menu |
| Mouse wheel | Zoom around the cursor |
Mass balance basics
The idea
Every arrow is a stream, every symbol with arrows going in and out is a unit. For every unit, what goes in must come out: solids, water and every metal. PfdLabs writes these balances for the whole diagram, fills in the values you did not enter and flags the units that do not close.
What you enter
- Click an arrow. In Stream data enter the stream number, the flow and the unit, and the % solids.
- In the Balance section choose the stream type (Slurry, Solution, Organic or Water) and, for slurries, the solids SG (default 2.8).
- Add components once per diagram (Cu %, Au g/t…) and enter grades on the streams you have assays for.

What PfdLabs calculates
| Result | From |
|---|---|
| Water, slurry mass and volume, pulp density | Solids flow, % solids and solids SG (see Slurry formulas) |
| Missing flows, % solids and grades | The balance of each unit, one unknown at a time |
| Concentrate and tailings flows | The two-product formula from grades |
| Metal flows, recovery, enrichment ratio, mass yield | Flows and grades (see Metal balance) |
| Circulating load | Recycle streams found in the diagram (see Circulating load) |
Calculated values are shown in purple and carry a calc tag on the arrow. Values you entered are shown in dark blue.
One unknown per unit
For each unit PfdLabs looks at all the streams around it. If exactly one value is missing (for example the flow of one stream), it is calculated from the others. The newly known value may then complete the balance of the next unit, so the calculation spreads through the whole flowsheet. It is repeated for solids, water and every component.
Balance check and warnings

| Badge | Meaning |
|---|---|
| ✓ balanced | Solids, water and every metal close within 0.5 %. |
| ⚠ out − in = −12 t/h | Solids do not close. More solids enter the unit than leave it (or the opposite). |
| ⚠ Cu out − in = −3.83 t/h | A metal does not close: flows × grades in and out differ. |
| ⚠ water out − in = +39 t/h | All water flows around the unit are known and they differ. If water is added (spray or wash water), draw it as a Water stream and leave it empty. |
| ⚠ negative flow in S7 | Closing the balance would need a negative flow. Check the values around the unit. |
The status button in the top bar counts the units with a warning: Mass & metal balance: OK or Mass balance: 2 warnings. Click it to open the stream table.

The stream table
Click the status button in the top bar to open the table under the diagram. It lists every stream with its type, solids, % solids, water, volume, pulp density and, for each component, grade, concentration, metal flow and recovery. Click a row to select the arrow. Export to Excel writes the same table and more.

Slurry formulas
Formulas
| Quantity | Formula | S6 example |
|---|---|---|
| Water | W = S × (100 − p) / p | 500 × 65 / 35 = 928.6 t/h |
| Slurry mass | M = S + W | 1 428.6 t/h |
| Solids volume | Vs = S / SG | 500 / 2.8 = 178.6 m³/h |
| Slurry volume | V = S / SG + W / 1.0 | 1 107.1 m³/h |
| Pulp density | ρ = M / V | 1.29 t/m³ |
| % solids from water | p = 100 × S / (S + W) | used when water is known from the balance |
S is the solids flow (t/h), p the solids content in % by weight, SG the specific gravity of the solids and W the water flow (t/h, equal to m³/h). Water density is taken as 1.0 t/m³.
Solids SG
Each slurry stream has its own Solids SG, by default 2.8. Concentrates are usually heavier than the ore, for example 4.1 for a copper concentrate. To set the same SG on every stream, use Apply to all in the stream table header.
Flow units
| Unit on the arrow | Used as |
|---|---|
| t/h | solids flow |
| kg/h | solids flow / 1 000 |
| t/d | solids flow / 24 |
| Mt/a | solids flow × 10⁶ / operating hours |
| m³/h, m³/d | flow of solutions and water |
Pipe velocity
For any stream, enter the inner pipe diameter in Pipe ID (mm) to get the velocity. Without a diameter, PfdLabs suggests the diameter for 2 m/s. Slurries below about 1.5 m/s may settle in the pipe and are marked in orange.
Metal balance and recovery
Components
- Open the stream table (status button in the top bar).
- Type the symbol, for example
Cu, choose its unit and click + Component. - The component appears as a field on every arrow. Enter the grades you know.
| Unit | Use for | Metal flow shown as |
|---|---|---|
| % | base metals, iron, sulphur | t/h and t/d |
| g/t | gold, silver, PGM | g/h and oz/d (troy) |
| ppm | trace elements | g/h and kg/d |
| g/L | only in solutions, e.g. H₂SO₄, NaCN | kg/h and t/d |
One component can be measured in two ways: as % (or g/t) in solids and as g/L in solutions. PfdLabs adds both into one metal flow, so leaching can be balanced from the ore to the cathode.
Formulas
| Result | Formula | Example (rougher) |
|---|---|---|
| Metal flow, % grade | m = S × g / 100 | 500 × 0.80 / 100 = 4.00 t/h Cu |
| Metal flow, g/t grade | m = S × g (g/h) | 500 × 0.30 = 150 g/h Au = 116 oz/d |
| Metal flow, solution | m = Q × C (kg/h) | 1 200 m³/h × 2.4 g/L = 2 880 kg/h |
| Recovery | R = m(product) / m(feed) × 100 | 3.64 / 4.00 = 90.9 % |
| Mass yield | Y = S(product) / S(feed) × 100 | 45.5 / 500 = 9.1 % |
| Enrichment ratio | ER = g(product) / g(feed) | 8.0 / 0.80 = 10.0 |
Where you see the results
| Place | What is shown |
|---|---|
| Arrow (Calculated box) | metal flow per hour and per day, recovery as % of the plant feed, calculated grades |
| Unit (Unit balance) | for each output: mass yield, recovery and enrichment ratio of each metal |
| Stream table | grade, metal flow and recovery columns for each component |
| Labels on the diagram | grades next to the flow, for example S7 · 45.5 t/h · Cu 8.0% |
Calculating unknown grades
Metal flows are balanced like solids: if one stream around a unit has no grade, its metal flow is calculated and divided by its solids flow to give the grade. This is how the grade of a final tailings or of a mixed stream is obtained.
Two-product formula
When to use it
On a plant you can usually measure the feed tonnage on a weightometer, and you get assays of the feed, concentrate and tailings from samples. The concentrate and tailings tonnages are rarely measured. The two-product formula fills this gap for any unit with one input and two outputs: a flotation bank, a cyclone, a spiral, a magnetic separator or a screen.
The formula
Two balances must hold at the same time:
| Balance | Equation |
|---|---|
| Solids | F = C + T |
| Metal | F·f = C·c + T·t |
Eliminating T gives the mass yield of the concentrate:
| Result | Formula |
|---|---|
| Mass yield | Y = (f − t) / (c − t) |
| Concentrate flow | C = F · Y |
| Tailings flow | T = F − C |
| Recovery | R = c (f − t) / [ f (c − t) ] |
| Enrichment ratio | ER = c / f |
Worked example
Rougher flotation from the Copper-gold concentrator template: the feed is 500 t/h at 0.80 % Cu, the rougher concentrate assays 8.0 % Cu and the tailings 0.08 % Cu.
| Step | Value |
|---|---|
| Y = (0.80 − 0.08) / (8.0 − 0.08) | 9.09 % |
| C = 500 × 0.0909 | 45.5 t/h |
| T = 500 − 45.5 | 454.5 t/h |
| R = 8.0 × 0.72 / (0.80 × 7.92) | 90.9 % |
| ER = 8.0 / 0.80 | 10.0 |
How to do it in PfdLabs
- Add the component once in the stream table: type
Cu, choose%, click + Component. - Click the feed arrow and enter the solids flow and the Cu grade.
- Click the concentrate and tailings arrows and enter only their Cu grades. Leave the flows empty.
- The two flows appear with a purple calc tag and the unit shows ✓ balanced. The unit panel says “Split calculated with the two-product formula from Cu grades”.
Accuracy and limits
The result is only as good as the assays. It is most sensitive when the feed grade is close to the tailings grade, which is typical for scavengers and low-grade ores:
| Tailings grade t | Mass yield | Concentrate C | Change |
|---|---|---|---|
| 0.07 % Cu | 9.21 % | 46.0 t/h | +1.3 % |
| 0.08 % Cu (base) | 9.09 % | 45.5 t/h | – |
| 0.09 % Cu | 8.98 % | 44.9 t/h | −1.2 % |
Circulating load
Definition
Why it matters
- Sizing: the mill, the cyclone feed pump and the cyclones are sized for the circulating flow, not for the fresh feed.
- Performance: typical ball mill – cyclone circuits run at 200–350 %. Too low gives a coarse product, too high overloads the mill and the pump.
- Plant data: the circulating load is usually calculated from % solids or size distributions of the cyclone feed, overflow and underflow. This is the two-product formula with water or a size fraction instead of a grade.
In PfdLabs
PfdLabs walks through the diagram from the feed. A stream that leads back to a unit already passed is a recycle. When its solids flow is known, a black badge ↻ Circulating load 250% appears next to it, placed where it does not cover other labels. Recycles below 1 % (for example a carbon loop) are not shown.

Solutions, SX and EW
Stream types
Select an arrow and choose its type at the top of the Balance section. The colour of the label shows the type.
| Type | Flow | Composition | Label colour |
|---|---|---|---|
| Slurry | t/h of solids + % solids | grades (%, g/t, ppm) | blue |
| Solution | m³/h (or t/h with SG) | g/L | cyan |
| Organic | m³/h | g/L | yellow |
| Water | m³/h | – | light blue |

SX/EW circuit
A unit with both an aqueous (solution) and an organic stream is treated as a solvent extraction stage. Its panel shows:
| Result | Formula | Template value |
|---|---|---|
| Aqueous in / out | Q of the solution streams | 1 200 / 1 200 m³/h |
| O/A ratio | Q organic / Q aqueous | 1 300 / 1 200 = 1.08 |
| Extraction | (m aq in − m aq out) / m aq in | (2 880 − 300) / 2 880 = 89.6 % |
| Transfer to organic | m aq in − m aq out | 2.58 t/h Cu |
| Organic loading | C stripped → C loaded | 5.92 → 7.90 g/L |
| Stripping | (m org in − m org out) / m org in | 25.1 % |

Electrowinning and precipitation
Draw the cathode (or a precipitate) as a Slurry stream with 100 % solids and its grade (Cu 100 %). PfdLabs calculates its flow from the metal balance: rich electrolyte minus lean electrolyte. Units fed only by solutions do not check the solids balance, because solids are formed there.
| Stream | Flow | Cu | Cu flow |
|---|---|---|---|
| Rich electrolyte | 400 m³/h | 48.0 g/L | 19.2 t/h |
| Lean electrolyte | 400 m³/h | 41.6 g/L | 16.6 t/h |
| Cathode | 2.58 t/h | 100 % | 2.58 t/h = 61.9 t/d |
Solution and water balance
For solutions, the liquid balance uses the solution mass (flow × SG). If a solution flow is missing, it is calculated from the liquid balance, and its concentration from the metal balance.
Water balance
Plant boundary
Water in is the water in all streams that leave units without inputs: ore moisture, process water, make-up water. Water out is the water in all streams that end in units without outputs: tailings, concentrate moisture, thickener overflow, filtrate, evaporation. The difference should be zero.

Water by unit
Green units close. For the others the difference is shown. A positive difference means more water leaves than enters: usually spray, wash or dilution water that is not on the diagram.
Calculating make-up water
- Draw the water addition as an arrow from a node such as “Process water” into the unit.
- Set its type to Water and leave the flow empty.
- Enter % solids on the other streams of the unit. The water addition is calculated and shown with a calc tag.
Time base and units
Flows per hour, day or year
In the stream table header choose Flows per hour / day / year and, for annual figures, the operating hours (for example 8 322 h/a = 95 % availability). Labels, panels, the stream table, the report and the Excel export are all converted. Annual values are scaled automatically to kt/a, Mt/a and koz/a.
| Hourly | Daily (× 24) | Annual (× 8 322 h) |
|---|---|---|
| 500 t/h ore | 12 000 t/d | 4.16 Mt/a |
| 3.24 t/h Cu | 77.8 t/d | 27.0 kt/a |
| 112 g/h Au | 86.5 oz/d | 30.0 koz/a |
Enter flows in any unit
The flow field on each arrow accepts t/h, m³/h, kg/h, t/d, m³/d and Mt/a. Mt/a is converted with the operating hours: 4.161 Mt/a at 8 322 h/a is 500 t/h.
Cases
Create a case
- Choose + New case… in the case selector in the top bar (or + Create a second case in the Cases tab).
- Name it. The current values become the Base case and the new case starts as a copy.
- Change only what differs, for example the feed 600 t/h instead of 500.
- Switch cases in the top bar. The diagram, panels, stream table and shared link show the active case.
The flowsheet, the arrows, stream types and stream numbers are the same in all cases. Only the input values change: flows, % solids, grades, concentrations and SG.
Compare

The comparison lists the plant feed, the solids, metal flow and recovery of every end product, the water entering the plant, the maximum circulating load and the number of warnings. Differences against the first case are in orange with the change in % (or in percentage points for recoveries).
Excel
The export contains a stream sheet for each case and a Cases sheet with the comparison.
Equipment sizing
How it works
Click a unit. Under its balance, Equipment sizing takes the feed of the unit from the balance (slurry volume and solids) and asks only for the design parameter. The method is suggested from the name of the unit and can be changed.

Tanks and flotation cells (residence time)
| Input | Meaning | Typical |
|---|---|---|
| Residence time t | minutes or hours | flotation 8–20 min (plant), leach and CIL 12–48 h |
| Number of units | the volume is split between them | |
| Air hold-up | share of the cell volume taken by air | flotation 10–20 % (default 15), tanks 0 |
| Scale-up factor k | lab to plant residence time | 1.5–2.5 for flotation |
Example: the rougher receives 1 238 m³/h (S6 plus flotation water). 12 min at 15 % air hold-up needs 291 m³, that is 4 × 72.8 m³.
Thickeners (solids flux)
| Result | Formula |
|---|---|
| Area | A = S / flux |
| Diameter | D = √(4A / π) |
| Unit area | A / (S × 24) m²/(t/d) |
| Rise rate | Q overflow / A m/h, orange above 3 m/h |

Filters (filtration rate)
A = S × 1 000 / rate / availability. 12.5 t/h of concentrate at 300 kg/m²/h and 85 % availability needs 48.9 m².
Pipes
See Slurry formulas → Pipe velocity.
All sizing results are in the Equipment sizing sheet of the Excel export and in the report.
Reagents and cost
Add reagents
- Click a unit, for example the rougher.
- Under Reagents click + Reagent, type its name, the dose and the price per kg.
- Choose the dose unit:
| Dose unit | Consumption |
|---|---|
| g/t ore | dose × plant feed solids / 1 000 (kg/h). This is how consumption is usually reported. |
| kg/t ore | dose × plant feed solids |
| g/t unit feed | dose × solids fed to this unit / 1 000, for example for cleaners |
| kg/h | fixed dosing |
Reagents tab

| Unit | Reagent | Dose | Consumption | Cost |
|---|---|---|---|---|
| Ball mill | Lime | 800 g/t | 400 kg/h | € 72/h |
| Rougher | PAX | 30 g/t | 15 kg/h | € 37.5/h |
| Rougher | MIBC | 25 g/t | 12.5 kg/h | € 26.3/h |
| Cleaner | PAX | 10 g/t | 5 kg/h | € 12.5/h |
| Total | € 148/h = € 0.30/t ore |
Choose the currency at the bottom of the tab (€, $, £, A$, C$, R, CLP$, PEN S/). The time base of the balance also applies here.
Sankey view
- In the top bar choose 👁 Sankey (flow widths).
- In the selector next to it choose the flow: Solids, Water or a component (Cu flow, Au flow…).
- The widest arrow carries the largest flow; the legend in the corner shows the maximum. Each label shows the flow and its % of the plant feed.

The Sankey view keeps your layout. It is exported to PNG and PDF and shown in shared links like the other view modes.
Data reconciliation
Why reconcile
Plant measurements always contain errors: weightometers drift, samples are not perfectly representative, assays have a precision. If you enter all flows and grades around a unit, they will rarely close exactly. Reconciliation finds the values closest to your measurements that satisfy every balance.
Method
PfdLabs minimises the weighted sum of squares of the adjustments
subject to the solids, water and metal balance of every unit (weighted least squares with Lagrange multipliers, iterated for the products of flow and grade). σ is the measurement error, set as a relative standard deviation for flows and for grades or concentrations (default 5 %). Values that are calculated, not measured, are free to move.
Reading the results

| Column / line | Meaning |
|---|---|
| Adjustment | reconciled − measured, in % |
| Adj. / σ | the adjustment in units of the measurement error. Above 2 it is shown in orange: a possible gross error. |
| Redundancy | number of balance equations minus unmeasured values. It must be at least 1. |
| SSQ and χ² limit | if SSQ is below the 95 % χ² limit, the measurements are consistent with their errors. |
Example
A rougher with measured flows 500 / 18 / 470 t/h, Cu 1.00 / 25.0 / 0.10 % and solids 33 / 30 / 30 % has a redundancy of 3. Reconciliation gives 494 / 17.96 / 476 t/h with SSQ 2.0, well below the limit of 7.8: the data are consistent. If the concentrate flow is entered as 28 t/h instead, SSQ rises to 22 and the concentrate flow and grade are marked in orange.
- Enter all measured values and set the measurement errors.
- Check the result and the values in orange. Correct obvious mistakes in the data.
- Click Apply reconciled values to replace the inputs with the reconciled values. Ctrl+Z brings the measurements back.
Report and Excel
Balance report
Click Report in the stream table or Export → Balance report. A new page opens; use Print / Save as PDF. It contains:
- title, date, active case, time base and status
- the whole diagram
- key results: plant feed, products, recoveries, water
- stream table and unit balances
- water balance, reagents, equipment sizing and reconciliation, when present

Excel workbook
| Sheet | Content |
|---|---|
| Stream table | all streams with flows, water, volume, density, grades, metal flows and recoveries |
| Unit balance | solids in, out, difference and status of every unit |
| Equipment sizing | feed and results of every sized unit |
| Reagents | doses, consumption and cost |
| Streams <case>, Cases | one sheet per case and the comparison |
Numbers are written as numbers, with units in the column headers, in the time base you selected. If Excel cannot be loaded, a CSV file is downloaded instead.
Plans
| Feature | Free | Pro Monthly | Pro Yearly | Pro Lifetime |
|---|---|---|---|---|
| Diagrams in the cloud | 5 | unlimited | unlimited | unlimited |
| All symbols, templates, Save as file | ✓ | ✓ | ✓ | ✓ |
| PNG and SVG export | with watermark | clean | clean | clean |
| PDF export | – | ✓ | ✓ | ✓ |
| Share read-only links | ✓ | ✓ | ✓ | ✓ |
| Mass & metal balance, water balance, SX/EW | – | – | ✓ | ✓ |
| Cases, sizing, reagents, Sankey, reconciliation, report | – | – | ✓ | ✓ |
| Price | €0 | €3 / month | €29 / year | €65 once |
Monthly subscribers can switch to Yearly in Dashboard → Manage billing. See Pricing for details.